Our Pool Construction Schedule
Transform Your Property Into an Oasis
Family and locally owned Greg's Pools & Spas can transform your backyard into an exquisite outdoor living space that will give you a lifetime of pleasure and enjoyment. Backed by over 46 years of experience in the pool construction business, we are expert pool builders in Covington, LA and the surrounding areas who are focused on delivering a high-quality product that you will enjoy.
You will receive the highest level of professionalism and workmanship. We work with you every step of the way to see that your expectations are met in the construction of your poolscape.
Set up an appointment with us and we will go over your desired location together, design a pool to fit that space comfortably and formulate a construction plan. Let the pool builders in Madisonville, LA and nearby towns help you custom design a beautiful new pool for your property.
The shell of the pool is guaranteed for life. The guarantee is non-transferable. Call us today for a free estimate.
Expected Construction Schedule
(Working Days)
- Day 1 - Your pool is dug, the forms are installed and the mud is spread or trucked off.
- Day 2 - Most of the steel is tied.
- Day 3 - We finish the steel and stub out the plumbing.
- Day 4 - Your pool is gunited.
- Day 5 - Cleanup day, forms are removed and gunite rebound is hauled away.
- Day 6 - Plumbing.
- Day 7 - The tile and coping is installed.
- Day 8 - Grading and compaction is done for decking.
- Day 9 - Form the deck.
- Day 10 - Deck inspection.
- Day 11 - Pour decking.
- Day 12 - Prep pool for plaster and wreck deck forms.
- Day 13 - The pool is plastered.
- Day 14 - Pool fills with water.
- Day 15 - Pump is started, and we add the chemicals and instruct you.
(Typical pool installation approximately three weeks.)
Share On: