| Expected Construction Schedule ( Working Days ) | | Day 1- | Your pool is dug, the forms are installed and the mud is spread or trucked off. | | Day 2- | Most of the steel is tied. | | Day 3- | We finish the steel, and stub out the plumbing. | | Day 4- | Your pool is gunited. | | Day 5- | Clean up day, forms are removed, and gunite rebound is hauled away. | | Day 6- | Plumbing. | | Day 7- | The tile and coping is installed. | | Day 8- | Grading and compaction is done for decking. | | Day 9- | Form the deck. | | Day 10- | Deck inspection. | | Day 11- | Pour decking. | | Day 12- | Prep pool for plaster and wreck deck forms. | | Day 13- | The pool is plastered. | | Day 14- | Pool fills with water. | | Day 15- | Pump is started, we add the chemicals and instruct you. | | (Typical pool installation approximately three weeks.) | | |